There are mechanical principles such as mutual proportions and upper and lower differences between machines. Reasonable mechanical principles are the main basis for giving full play to the machine's own capabilities. Therefore, a set of concrete mixing plants can achieve the maximum output based on reasonable concrete mixing plant mechanical principles.
Concrete mixing plants are divided into four parts: sand and gravel feeding, powder (cement, fly ash, expansion agent, etc.) feeding, water and admixture feeding, transmission mixing and storage.
1. Steps of the mixing station workflow
1. After the mixer control system is powered on, enter the human-machine dialogue operation interface
2. The system is initialized, including formula number, concrete grade, slump, production volume, etc.
3. According to the weighing, each silo and metering hopper are inspected, and the empty or full signal is output to prompt the operator to determine whether to start the mixing control program
4. Start the sand and stone belt motor to feed the metering hopper
5. Open the butterfly valve of the fly ash and cement tank
6. Start the screw motor to transport fly ash and cement to the metering hopper
7. Open the control valve of the water tank and admixture tank to allow water and admixture to flow into the metering hopper
8. Open the metering hopper door after the metering meets the set requirements
9. The ingredients enter the started mixer for mixing and mixing. When the set time comes, open the mixer door and the concrete enters the mixer truck that has received the materials.
Each machine has a switching sequence. If it is not operated properly, it will cause a lot of trouble. The switching sequence of the concrete mixing station is very important. If it is not operated properly, the concrete mixing station will be shut down, the machine will be blocked, etc., resulting in machine repair and maintenance.
Detailed Steps For Safe Operation Of Concrete Mixing Station